The work of Helmand Hydro dam will get end soon


 
 

The reconstruction work of Helmand Hydro dam go up to 80% and will get complete soon.

Upon completion of this work, the generative capacity of this dam will increase from 1.5 megawatts to 4.8 megawatts.

The contract was signed between DABS and India and China HUNAN-AIPI GV in 2012 and is scheduled to be completed and put into operation by the end of June 2018.

The Greshk electricity grid project costs US $ 43 million, which is funding by ADB's assistance to the Afghan government.

 Upon the completion of this project, 5,000 subscribers in the city of Greshk and the surrounding villages will connects to new the electricity.