Inauguration of 220KV Transmission line and 220/20 Substation of Logar


 
 

H.E Mohammad Ashraf Ghani, President of Islamic Republic of Afghanistan, inaugurated 220 KV Kabul – Logar transmission line and logar substation 220/20 KV.

In this ceremony, some ministers, national assembly member and logar province assembly, elders and Breshna staff were participated.
The transmission line of 220KV from Arghandi Kabul – Pul Alem city, have nearly 72Km lengths, and 246 installed towers on way.
The capacity of 220KV transmission line, is 32mega watt, currently the diesel grantor power is around 2000, in near future the consumer number will extend more.
The construction of distribution power line of Pul Alem city for 13000 is also in progress, the the detail study survey is complete and its design is also finalized and the tools and stuff is going to settle and set till April 2019.
Point to be mention that the consultancy companies are: SMEC Consultancy Company and Jaguar Overseas Limited.
This project estimated cost is 23.89 Million USD, that are from exchange assistant and fund of Asian Development Bank.
By adding 13000 new customers beside other resident, opportunity for industrialist and trade will be more improve.