construction of substation in Arghandi_Kabul


 
 

20 May 2018

The work of 220/20KV substation in Arghandi Kabul, which is 126 MW, has gone up 90 percent now, and it is currently underway and after completion will put into operation in the near future.

The contract was signed on June 28, 2016 between DABS and SIEMENS, and is scheduled to be completed by June 28, 2018.

The project costs $ 20.2 million, which is funded by Asian Development Bank (ADB).

Upon completion of the project, a total of 80000 subscribers will be connected to new electricity

The project will have positive effects on economic growth, security, local people, changes and improvement in the lives of citizens.