Progress in supply of goods for the electrification network of Herat


 
 

The 20/0.4 KV electrification network in four districts (Chesht-e-Sharif, Hobai, Karokh and Pashton Zarghoon) of Herat province started on 27th of December 2017. With the completion of this project approximately 123000 residents in the four respective districts of Herat will benefit from electricity. It is one of the key electricity projects of Da Afghanistan Breshna Sherkat (DABS) and currently 80% of the project works are completed.
The third LOT of this project includes supply of goods for the 20/0.4 KV electrification network in Chesht-e-Sharif, Hobai, Karokh and Pashton Zarghoon districts of Herat. This project will cost around 4 million USD which is funded by the World Bank and will be completed on 27 of September 2018. DABS is committed in providing better facilities to Afghans through electricity projects.