Project progress of Bamyan substation and expansion of Doshi substation in Baghlan


 
 

The 220/20 KV Bamyan substation and expansion of Doshi substation in Baghlan project started on 11th of January 2019. With the successful completion of this project approximately 20000 will benefit from electricity. 
This project is one of the major projects of Da Afghanistan Breshna Sherkat (DABS). Currently 8 percent of the project works are completed. The contract of this project was signed with the Chinese company XEPC on 22 of April 2018. This project will cost around 11.7 million USD which is funded by the Asian Development Bank and will be completed on 11 of January 2021. 
DABS is committed in providing better facilities to Afghans through electricity projects.