Project progress of Andkhoy, Sheberghan and expansion of Mazar-e-Sharif Substation


 
 

The Andkhoy, Sheberghan and expansion of Mazar-e-Sharif substation project started on 20th of July 2016. Currently 99 percent of the project works are completed and the testing and commissioning stages are in progress.
With the successful completion of this project approximately 100000 residents in Andkhoy, Sheberghan, Mazar-e-Sharif and areas including in this project will benefit from electricity.
The contract of this project was signed between Da Afghanistan Breshna Sherkat (DABS) and Siemens Construction Company on 17 November 2015.
This project is one of the major projects of Da Afghanistan Breshna Sherkat (DABS). The project will cost around 35 million USD which is funded by the Asian Development Bank and will be completed on 31 of January 2019.
DABS is committed in providing better facilities to Afghans through electricity projects.