Accelerating the Practical Work of 220 KV Salang Substation and 20 KV Distribution Network Project


 
 

In order to further coordinate to accelerate the remaining work of 220 KV Salang substation and 20 KV distribution network project, a joint meeting was held at the headquarters of DABS.

The meeting was attended by Eng. Amanullah Ghalib, Chief Executive Officer of De Afghanistan Breshna Sherkat, Supervisory Team, DABS Technical Officials and Project Contractor team.

Mr. Ghalib instructed to the relevant authorities to accelerate their finances affairs, more and better preparations to energize the above mentioned station

Supervision teams of Breshna said that the practical work of 220 KV Salang Tunnel substation and its distribution network with a capacity of 8 MW will benefit Salang Tunnel is about finished.

And it's going to be experimentally powered by the end of this month and after its trial period, will put into operation in the near future.

It is to be noted that the project is funded by the United States Development Agency (USAID) at a cost of more than $ 20 million.