Regeneration of water power dam in Greshk district is ongoing


 
 

In Greshk district of Helmand province, power capacity rises from 1.5 MW to 8.4 MW.

The contract of reconstruction of the Greshk water power plant was signed between DABS and AIBL-HUNAN ALLONWARG-JV company in 2012 India and China country, and these projects have been scheduled to be completed and operational until 2017.

The project’s cost 38 million USAD dollar, which is funded by the budget of ADB to the Afghanistan government.

Upon completion of Greshk water power dam, 5000 subscribers will be connected to power.

It should be noted that, the work of mentioned project in 2014 should be completed, but was delayed due to security problems in the project area.