Development of power energy in Panjshir


 
 

Da Afghanistan Breshna Sherkat continued to provide power services in near and far points of the country, this time expanded 20.4 kV network in the center of Panjshir province.

This network has been installed with the capacity of 4.8 MW, 22 Transformers, 488 concrete and metallic which is 20KV, 226 metallic which is 4.0KM, 256 Brackets and 707 Insulators.

The mentioned project costs nearly US $ 5 million, which is funded by DABS.

The work of this project had begun in 2014 and shortly will be completed then will put into operation.

With the expansion of mentioned network, more than 6,000 subscribers will be benefited in Panjshir province.